Visit Open-E website
Results 1 to 6 of 6

Thread: scheduled snapshot

Hybrid View

Previous Post Previous Post   Next Post Next Post
  1. #1

    Default

    You ca not set each snapshot to run for a whole week... you can assign 7 snapshots for 7 days. as each snapshots can be set for 24 hours... You can set this schadual to run weekly.

  2. #2
    Join Date
    Jan 2008
    Posts
    33

    Default

    Quote Originally Posted by SuperSAN
    You ca not set each snapshot to run for a whole week... you can assign 7 snapshots for 7 days. as each snapshots can be set for 24 hours... You can set this schadual to run weekly.
    I do not agree - if snapshot is gig enough then could be able to run whole week. Just create 7 snapshots and schedule one to be activated in Monday with start for example at 7:00 AM and stop at 6:50 AM, one in Tuesday with the same time, etc... Such snapshots will work for 7 days.

  3. #3

    Default

    Hello!

    I want the snapshot from Monday be accessable on Thursday (for example). And on next Monday a new snapshot should be scheduled.

  4. #4
    Join Date
    Jan 2008
    Posts
    33

    Default

    So configure one big snapshot with start at 6:00 AM and stop at 5:50 AM on Monday.

  5. #5

    Default

    Thx, that works!

    Now I have 6 snapshots Monday 6:00 to Monday 5:55 up to Saturday.

    Works fine so far!!

    Regards
    Manfred